108” C200 welded steel carrier pipe on the Integrated Pipeline Project. The pipe was pushed through the casing via a rail skid system and butt welded at each joint. The annular space in the tunnel was then filled with grout via grout ports located on the carrier pipe. Learn more at www.thompsonpipegroup.com. Video courtesy Tarrant Regional Water District.